Law4u - Made in India

Can COVID-19 be considered a valid reason for breach of contract?

12-Dec-2025
Breach of Contract

Answer By law4u team

The COVID-19 pandemic has caused massive disruptions across industries globally, leading to widespread economic challenges, supply chain disruptions, and restrictions on movement. As businesses and individuals navigate these uncertainties, many have questioned whether COVID-19 can be considered a valid reason for the breach of contract. The answer to this largely depends on the specific circumstances of the contract, the nature of the breach, and the applicable legal doctrines. In India, and in many other jurisdictions, the possibility of COVID-19 leading to the breach of contract is often considered through the lens of force majeure and frustration of contract. Let’s delve deeper into these two legal concepts to understand when COVID-19 could potentially serve as a valid excuse for not fulfilling contractual obligations. 1. Force Majeure Clause and COVID-19 A force majeure clause in a contract is a provision that relieves one or both parties from liability for non-performance or delay in performance due to events beyond their control. These events are typically unpredictable, unavoidable, and often classified as acts of God (e.g., natural disasters like floods or earthquakes) or other extraordinary circumstances (e.g., war, strikes, pandemics). COVID-19 can potentially be considered a force majeure event if the contract specifically includes a pandemic or similar unforeseen events as part of its force majeure clause. To invoke the force majeure clause and justify a breach of contract, the affected party must prove the following: Impossibility of Performance: The party seeking to invoke the clause must show that the COVID-19 pandemic has made it impossible to fulfill the contractual obligations. For example, a lockdown might make it impossible for a business to operate, or travel restrictions may prevent the shipment of goods. Notification Requirement: Most force majeure clauses require that the affected party notify the other party about the inability to perform on time due to force majeure events. It is essential to communicate this promptly to avoid breaching the contract. Mitigation of Effects: The party invoking force majeure must demonstrate that they took reasonable steps to mitigate the effects of the pandemic. For instance, they might need to show they tried to work around the restrictions or delay the performance instead of failing entirely. If the contract has a force majeure clause that covers pandemics or emergencies like COVID-19, it is likely that the pandemic could be considered a valid reason for non-performance or delayed performance. 2. Doctrine of Frustration of Contract In cases where the contract does not contain a force majeure clause, the doctrine of frustration under Section 56 of the Indian Contract Act, 1872 may come into play. This legal principle provides that if the performance of a contract becomes impossible or illegal due to unforeseen circumstances, the contract may be considered frustrated and void. Under Section 56, a contract may be frustrated if: Performance Becomes Impossible: If due to COVID-19, it becomes physically impossible to perform the contract (for example, a construction project where workers are unable to attend due to lockdowns), then the contract may be considered frustrated. Radical Change in Circumstances: If the contract’s fundamental purpose is destroyed by COVID-19 (e.g., an event that was the subject of the contract is canceled because of government-imposed restrictions), frustration may be invoked. For example, if an event management company is hired to organize a conference, but due to COVID-19 restrictions, it is illegal to hold the event, the contract could be frustrated. Key Elements of Frustration: Unforeseeability: The event (COVID-19 pandemic) must be unforeseeable at the time the contract was made. Since the pandemic was unprecedented, it qualifies as an unforeseeable event for most contracts made before the pandemic. Impossibility: It is not enough for the performance to be difficult or expensive; it must be impossible. A mere increase in cost or delay does not frustrate a contract; the performance must be rendered physically impossible by the event. Not due to Fault: The party invoking frustration must prove that the breach was not due to their own fault or negligence. The party must show that they were unable to perform due to circumstances entirely beyond their control. 3. COVID-19 as a Ground for Breach of Contract: Examples and Scenarios Here are a few common scenarios where COVID-19 may be considered a valid reason for the breach of contract: 1. Non-delivery of Goods: A supplier in one country might be unable to deliver goods due to shipping restrictions caused by COVID-19. The inability to deliver the goods on time could be covered under a force majeure clause if the pandemic or related restrictions are specified as an excusable event. 2. Event Cancellations: Many contracts for events (conferences, weddings, festivals) have been disrupted because of COVID-19. Event organizers may be excused from performing their obligations if government restrictions make it impossible to hold the event, thus triggering the doctrine of frustration. 3. Contractual Service Disruptions: A service provider may invoke force majeure if they are unable to fulfill a service agreement due to government-imposed lockdowns or travel restrictions. For example, a consultancy may not be able to travel to another country to offer services as per the contract due to travel bans. 4. Failure to Perform Due to Workforce Shortages: In cases where an employer or contractor cannot provide services due to a shortage of workers (because of illness, quarantine, or lockdowns), they might argue that performance became impossible or significantly delayed. 4. Limitations and Considerations While COVID-19 may justify a breach of contract in some cases, the affected party cannot simply claim force majeure or frustration without considering the following: Interpretation of Contract Terms: A court will consider the specific terms of the contract, including the force majeure clause (if any) and any definitions related to events like pandemics, natural disasters, or emergencies. Mitigation of Losses: The party invoking force majeure or frustration must show that they mitigated their losses as much as possible. This could mean negotiating an alternative solution with the other party, requesting extensions, or exploring other ways to fulfill the contract. Temporary Suspension vs. Total Breach: In many cases, courts may allow temporary suspensions or extensions rather than a total breach, provided that the breach is due to an event like COVID-19. If the situation improves, the parties may still be required to perform under the contract. Legal Jurisdictions and Precedents: The approach to COVID-19 and breach of contract may vary based on local laws, judicial precedents, and the jurisdiction in which the contract is enforced. Courts in some jurisdictions may be more lenient with respect to COVID-19, while others may be stricter in their interpretation. Conclusion COVID-19 can be considered a valid reason for breach of contract under certain circumstances, primarily through the force majeure clause or the doctrine of frustration. If the contract includes a force majeure provision that covers pandemics or emergencies, businesses and individuals affected by the pandemic may be excused from performance. Alternatively, under the doctrine of frustration, a contract may be voided if the pandemic has rendered performance impossible or the contract’s core purpose is destroyed. However, it is important to carefully review the terms of the specific contract, ensure proper documentation, and demonstrate that the breach was truly due to COVID-19-related factors and not due to other issues. As the legal landscape around COVID-19 continues to evolve, consulting with legal professionals to assess the specific facts of the case is highly recommended.

Answer By Anik

Dear client, The outbreak of the COVID-19 have led to a severe breakdown of commercial activities in India. There has been a lot of controversy that has sparked on the point if COVID-19 can be considered as a valid reason for the breach of contract. The answer depends heavily on the specific circumstances of the contract, the nature of the breach and the applicable legal doctrines. Force Majeure Clause The term ‘force majeure’ is of much wider import and the intention is to save the performing party from the consequences of anything over which he has no control . The law does not compel a man to do which he cannot possibly perform. It excuses the promisor from performing its obligations under the contract, without the attendant consequences of breach of liability for paying damages.It could be understood that force majeure is related to a temporary event. Doctrine of frustration The doctrine of frustration may mean that a contract is discharged in entirety where, for instance, the fundamental commercial basis/substratum to the contract ceases to exist. A force majeure event thus, may ultimately result in the contract being terminated for frustration. However, force majeure in itself, does not mean that the contract is frustrated from the inception of its invocation. COVID-19 and Force Majeure Clause The outbreak of COVID-19 was declared a Public Health Emergency of International Concern on January 30, 2020 by the World Health Organisation (“WHO”) and government has recognized that COVID-19 constitutes a ‘disaster’ under the Disaster Management Act, 2005 and is of such a nature or magnitude so as to be beyond the control of individuals and the community and accordingly, has restricted the movement of people in India and order for closure of commercial and industrial establishments. Thus it could be concluded that COVID-19 constitutes a force majeure event. Force majeure have been included as express terms of an agreement or not and where it is included, COVID-19 may constitute an event of force majeure. However, every contract is different and a generalized interpretation of ‘force majeure’ including COVID-19 as an even constituting force majeure cannot be provided. Where the contract is silent on the terms of force majeure and for invocation of force majeure, only on satisfaction of the penta-test of implied terms, can it be read into a contract. It is also to be seen whether COVID-19 will stand the test of court of being a notified disaster constituting an event of force majeure or whether it will only constitute an event that has led to contractual obligations becoming onerous or costly to perform. I hope this answer was helpful. For any further queries please do not hesitate to contact us.

Answer By Ayantika Mondal

Dear client, Covid - 19 does not automatically excuse a breach of contract. Broadly it can be relevant under two legal heads: Force Majeure, and Doctrine of Frustration. 1. Force Majeure: if a contract contains a force majeure clause, covid -19 and other government related actions like lockdown, travel bans and so on, then it may qualify as force majeure event. Provided that the clause needs to be expressly mentioned. Therefore in such cases non performance may be excused. 2. Doctrine of Frustration: when there is no force majeure clause, a party may rely on the doctrine of frustration under Section 56 of the Indian Contract Act, 1872. Therefore covid - 19 may frustrate a contract if performance has become impossible, or unlawful. I hope this answer was helpful. For further queries, please do not hesitate to contact us. Thank you.

Breach of Contract Verified Advocates

Get expert legal advice instantly.

Advocate Lekh Narayan Karna

Advocate Lekh Narayan Karna

Breach of Contract, Cheque Bounce, Corporate, Criminal, Documentation, High Court, Labour & Service, Landlord & Tenant, NCLT, Recovery, Trademark & Copyright

Get Advice
Advocate Mohd Imran

Advocate Mohd Imran

Anticipatory Bail, Breach of Contract, Cheque Bounce, Child Custody, Civil, Consumer Court, Court Marriage, Criminal, Cyber Crime, Divorce, Domestic Violence, Family, High Court, Motor Accident, Muslim Law, Property, Succession Certificate

Get Advice
Advocate Dhiraj S Pawar

Advocate Dhiraj S Pawar

Anticipatory Bail, Banking & Finance, Breach of Contract, Cheque Bounce, Civil, Consumer Court, Criminal, Divorce, Documentation, Domestic Violence, Family, High Court, Insurance, Landlord & Tenant, NCLT, Property, R.T.I, RERA, Succession Certificate, Trademark & Copyright, Wills Trusts, Revenue

Get Advice
Advocate Asawary

Advocate Asawary

Anticipatory Bail, Bankruptcy & Insolvency, Banking & Finance, Child Custody, Court Marriage, Cheque Bounce, Breach of Contract, Civil, Consumer Court, Corporate, Divorce, Documentation, Domestic Violence, Family, High Court, Motor Accident, R.T.I, Recovery, RERA, Startup, Landlord & Tenant, Succession Certificate, Wills Trusts, Revenue, Insurance

Get Advice
Advocate Ashutosh Jha

Advocate Ashutosh Jha

Anticipatory Bail, Arbitration, Armed Forces Tribunal, Bankruptcy & Insolvency, Banking & Finance, Breach of Contract, Cheque Bounce, Child Custody, Civil, Consumer Court, Corporate, Court Marriage, Customs & Central Excise, Criminal, Cyber Crime, Divorce, Documentation, GST, Domestic Violence, Family, High Court, Immigration, Insurance, International Law, Labour & Service, Landlord & Tenant, Media and Entertainment, Medical Negligence, Motor Accident, Muslim Law, NCLT, Patent, Property, R.T.I, Recovery, RERA, Startup, Succession Certificate, Supreme Court, Tax, Trademark & Copyright, Wills Trusts, Revenue

Get Advice
Advocate Utsav Kumar Mishra

Advocate Utsav Kumar Mishra

Anticipatory Bail, Arbitration, Armed Forces Tribunal, Bankruptcy & Insolvency, Banking & Finance, Breach of Contract, Cheque Bounce, Child Custody, Civil, Consumer Court, Corporate, Court Marriage, Customs & Central Excise, Criminal, Cyber Crime, Divorce, Documentation, GST, Domestic Violence, Family, High Court, Immigration, Insurance, International Law, Labour & Service, Landlord & Tenant, Media and Entertainment, Medical Negligence, Motor Accident, Muslim Law, NCLT, Patent, Property, R.T.I, Recovery, RERA, Startup, Succession Certificate, Supreme Court, Tax, Trademark & Copyright, Wills Trusts, Revenue

Get Advice
Advocate Vishal Mohanrao Janrao

Advocate Vishal Mohanrao Janrao

Anticipatory Bail, Arbitration, Armed Forces Tribunal, Bankruptcy & Insolvency, Banking & Finance, Breach of Contract, Cheque Bounce, Child Custody, Civil, Consumer Court, Corporate, Court Marriage, Customs & Central Excise, Criminal, Cyber Crime, Divorce, Documentation, GST, Domestic Violence, Family, High Court, Immigration, Insurance, International Law, Labour & Service, Landlord & Tenant, Media and Entertainment, Medical Negligence, Motor Accident, Muslim Law, NCLT, Patent, Property, R.T.I, Recovery, RERA, Startup, Succession Certificate, Supreme Court, Tax, Trademark & Copyright, Wills Trusts, Revenue

Get Advice
Advocate M A Rahim

Advocate M A Rahim

Anticipatory Bail, Breach of Contract, Cheque Bounce, Civil, Consumer Court, Criminal, Divorce, Cyber Crime, Documentation, High Court, Family, Domestic Violence, Labour & Service, Landlord & Tenant, Media and Entertainment, Property, Revenue

Get Advice
Advocate Rajashekar N M

Advocate Rajashekar N M

Cheque Bounce, Documentation, Criminal, Domestic Violence, Breach of Contract, Family, Landlord & Tenant, Property, Revenue, Consumer Court, Motor Accident, Succession Certificate, Bankruptcy & Insolvency

Get Advice
Advocate Rajesh Doshi

Advocate Rajesh Doshi

Anticipatory Bail, Breach of Contract, Banking & Finance, Consumer Court, Court Marriage, Divorce, Family, Media and Entertainment, Succession Certificate, Wills Trusts, Criminal, Property, R.T.I

Get Advice

Breach of Contract Related Questions

Discover clear and detailed answers to common questions about Breach of Contract. Learn about procedures and more in straightforward language.